	<title>Kontraktor Archives - Portal Luwuk</title>
	<atom:link href="https://portalluwuk.com/tag/kontraktor/feed/" rel="self" type="application/rss+xml" />
	<link>https://portalluwuk.com/tag/kontraktor/</link>
	<description>Satu Untuk Semua</description>
	<lastBuildDate>Thu, 01 Feb 2024 15:04:00 +0000</lastBuildDate>
	<language>id</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	<generator>https://wordpress.org/?v=6.5.5</generator>

<image>
	<url>https://portalluwuk.com/wp-content/uploads/2022/12/portalluwuk2-90x90.png</url>
	<title>Kontraktor Archives - Portal Luwuk</title>
	<link>https://portalluwuk.com/tag/kontraktor/</link>
	<width>32</width>
	<height>32</height>
</image> 
	<item>
		<title>Masuk Finishing, Kontraktor Proyek DTW Kilo 5 Luwuk Minta Tambahan Waktu 20 Hari Lagi</title>
		<link>https://portalluwuk.com/masuk-finishing-kontraktor-proyek-dtw-kilo-5-luwuk-minta-tambahan-waktu-20-hari-lagi/</link>
					<comments>https://portalluwuk.com/masuk-finishing-kontraktor-proyek-dtw-kilo-5-luwuk-minta-tambahan-waktu-20-hari-lagi/#respond</comments>
		
		<dc:creator><![CDATA[Admin]]></dc:creator>
		<pubDate>Thu, 01 Feb 2024 14:59:54 +0000</pubDate>
				<category><![CDATA[Info PUPR]]></category>
		<category><![CDATA[20 Hari]]></category>
		<category><![CDATA[Kontraktor]]></category>
		<category><![CDATA[Masuk Finishing]]></category>
		<category><![CDATA[Proyek DTW Kilo 5]]></category>
		<category><![CDATA[Tambah Waktu]]></category>
		<guid isPermaLink="false">https://portalluwuk.com/?p=6140</guid>

					<description><![CDATA[<p>PORTAL LUWUK &#8211; Proyek monumental Daerah Tujuan Wisata...</p>
<p>The post <a href="https://portalluwuk.com/masuk-finishing-kontraktor-proyek-dtw-kilo-5-luwuk-minta-tambahan-waktu-20-hari-lagi/">Masuk Finishing, Kontraktor Proyek DTW Kilo 5 Luwuk Minta Tambahan Waktu 20 Hari Lagi</a> appeared first on <a href="https://portalluwuk.com">Portal Luwuk</a>.</p>
]]></description>
										<content:encoded><![CDATA[
<p><strong>PORTAL LUWUK &#8211; </strong>Proyek monumental Daerah Tujuan Wisata (DTW) Kilo 5 Luwuk, selangkah lagi masuk tahap finishing oleh kontraktor penyedia PT Makmur Sulteng Raya. Proyek yang dibandrol Rp11,9 miliar itu teranggarkan pada Tahun 2023 lalu.</p>



<p>Hingga kini, memasuki bulan Februari 2024, proyek tersebut belum juga selesai dirampungkan. Kini baru memasuki tahap Finishing alias masa akhir pengerjaan.</p>



<p> &#8220;Kontraktornya masih meminta tambahan waktu 20 hari lagi. Diperkirakan Tanggal 20 Februari seluruh item kegiatan selesai dikerjakan,&#8221;kata I Putu Jati Arsana kepada <a href="http://Portalluwuk.com">Portalluwuk.com</a>, Selasa (30/1/2024).</p>



<p>Sebelum masa kontrak berakhir 2023 lalu, kontraktor penyedia sempat diberikan perpanjang waktu selama 50 hari, disertai sanksi denda setiap hari. </p>



<p>&#8220;Karena tak cukup waktu dan masih ada item yang belum bisa diselesaikan, mereka meminta lagi tambahan waktu 20 hari kerja,&#8221;terang Putu yang kini menjabat Kepala Bidang Penataan Bangunan dan Infrastruktur Permukiman Dinas PUPR Banggai ini.</p>



<p>Pantauan media ini, lokasi proyek berlantai dua ini dibangun disempadan pantai tanpa reklamasi karena menerapkan kontruksi tiang pancang. Bagunan megah ini akan menampung eks pedagang dan memungkinkan ditempati calon usaha baru.</p>



<p>&#8220;Yang akan menempati itu, sesuai petunjuk pimpinan diprioritaskan pada eks pedagang. Pedagang lain kemungkinan ada, namun belum ada petunjuk lanjut terkait pendaftarannya. Kemungkinan dikenakan sewa bangunan kepengguna sebagai pemasukan bagi daerah,&#8221;kata Kadis Pariwisata Ismet Wardana kepada media ini beberapa waktu lalu.*</p>
<p>The post <a href="https://portalluwuk.com/masuk-finishing-kontraktor-proyek-dtw-kilo-5-luwuk-minta-tambahan-waktu-20-hari-lagi/">Masuk Finishing, Kontraktor Proyek DTW Kilo 5 Luwuk Minta Tambahan Waktu 20 Hari Lagi</a> appeared first on <a href="https://portalluwuk.com">Portal Luwuk</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://portalluwuk.com/masuk-finishing-kontraktor-proyek-dtw-kilo-5-luwuk-minta-tambahan-waktu-20-hari-lagi/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		
			</item>
		<item>
		<title>Proyek DTW Kilo 5 Luwuk Alami Deviasi Minus, Kontraktor PT MSR Pacu Pengerjaanya</title>
		<link>https://portalluwuk.com/proyek-dtw-kilo-5-luwuk-alami-deviasi-minus-kontraktor-pt-msr-pacu-pengerjaanya/</link>
					<comments>https://portalluwuk.com/proyek-dtw-kilo-5-luwuk-alami-deviasi-minus-kontraktor-pt-msr-pacu-pengerjaanya/#respond</comments>
		
		<dc:creator><![CDATA[Admin]]></dc:creator>
		<pubDate>Mon, 15 Jan 2024 13:17:30 +0000</pubDate>
				<category><![CDATA[Info PUPR]]></category>
		<category><![CDATA[Alami]]></category>
		<category><![CDATA[Deviasi Minus]]></category>
		<category><![CDATA[DTW Kilo 5 Luwuk]]></category>
		<category><![CDATA[Kontraktor]]></category>
		<category><![CDATA[Pacu]]></category>
		<category><![CDATA[Pengerjaanya]]></category>
		<guid isPermaLink="false">https://portalluwuk.com/?p=5643</guid>

					<description><![CDATA[<p>PORTAL LUWUK &#8211; Pekerjaan Penataan Lanscape DTW (Daerah...</p>
<p>The post <a href="https://portalluwuk.com/proyek-dtw-kilo-5-luwuk-alami-deviasi-minus-kontraktor-pt-msr-pacu-pengerjaanya/">Proyek DTW Kilo 5 Luwuk Alami Deviasi Minus, Kontraktor PT MSR Pacu Pengerjaanya</a> appeared first on <a href="https://portalluwuk.com">Portal Luwuk</a>.</p>
]]></description>
										<content:encoded><![CDATA[
<p><strong>PORTAL LUWUK &#8211; </strong>Pekerjaan Penataan Lanscape DTW (Daerah Tujuan Wisata) Kilo 5 di Kecamatan Luwuk Selatan, Banggai, Sulawesi Tengah mengalami deviasi minus dari target yang ditetapkan. Akibatnya terjadi keterlambatan pengerjaan proyek hingga menyeberang tahun 2024.</p>



<p>Pembangunan gedung monumental berlantai tiga tersebut dianggarkan Rp11,9 miliar lebih oleh Dinas Pekerjaan Umum dan Penataan Ruang (PUPR) Kabupaten Banggai melalui Anggaran Pendapatan Belanja Daerah (APBD) Tahun 2023 dan dikerjakan rekanan pemenang tender PT Makmur Sulteng Raya (MSR).</p>



<p>Adapun dokumen waktu kontrak sebagaimana tercantum dalam papan proyek terhitung mulai tanggal 3 Agustus 2023. Hingga saat ini Januari 2024, proyek dimaksud belum juga rampung dikerjakan seratus persen. Namun keterlambatan tersebut tentu bukan tanpa alasan.</p>



<p>Pihak konsultan proyek, Jamal, mengungkapkan, proyek tersebut terjadi deviasi minus karena adanya keterlambatan pengiriman bahan pabrikasi tiang pancang yang dipesan dari perusahan WK Beton di Makassar, Sulawesi Selatan.</p>



<p>Dimana dari rencana pemancangan dimulai awal minggu ke 4 Agustus dan baru tiba dilokasi proyek dan baru dilaksanakan pemancangan pada minggu ke 8 September hingga minggu ke 12 Oktober 2023.</p>



<p>&#8220;Mobilisasi tiang pancang dari Makassar-Luwuk dilaksanakan dua tahap, yakni minggu ke 8 dan minggu ke 12,&#8221;kata Jamal, belum lama ini.</p>



<p>Menurutnya dengan adanya keterlambatan ini sangat berpengaruh pada penyelesaian pekerjaan. &#8220;Sangat berpengaruh,&#8221;ucapnya.</p>



<p>Ia menuturkan, untuk menyelesaian pekerjaan tersebut tergantung komitmen dari kontraktor pelaksana selaku pihak penyedia. &#8220;Tapi umumnya pekerjaan yang lambat akan diberi batas waktu yg telah ditentukan. Dan berlaku pula aturan denda setiap harinya,&#8221;sebutnya.</p>



<p>Pantauan media ini, pengerjaan proyek tersebut terus dipacu dengan adanya ketambahan waktu pekerjaan. Bangunan berlantai tiga yang dibangun ditepian pantai tersebut cukup megah dan menjadi kebanggan warga Kota Luwuk.*</p>
<p>The post <a href="https://portalluwuk.com/proyek-dtw-kilo-5-luwuk-alami-deviasi-minus-kontraktor-pt-msr-pacu-pengerjaanya/">Proyek DTW Kilo 5 Luwuk Alami Deviasi Minus, Kontraktor PT MSR Pacu Pengerjaanya</a> appeared first on <a href="https://portalluwuk.com">Portal Luwuk</a>.</p>
]]></content:encoded>
					
					<wfw:commentRss>https://portalluwuk.com/proyek-dtw-kilo-5-luwuk-alami-deviasi-minus-kontraktor-pt-msr-pacu-pengerjaanya/feed/</wfw:commentRss>
			<slash:comments>0</slash:comments>
		
		